For a standard house foundation in Ireland, the safest answer is a specified ready mix concrete, with the grade confirmed by your engineer before the pour. Irish building guidance sets C12/15 as the minimum for plain, unreinforced strip foundations in non-aggressive ground. Reinforced foundations follow the grade on the engineer’s drawings. A hand-mixed 1:7 cement to aggregate mix is only allowed for small jobs. Below, we explain what those terms mean, how to choose, and what to check when the lorry is booked.
- Plain strip foundations in non-aggressive ground need at least C12/15 concrete (15 N/mm²), with a minimum of 200 kg of cement per cubic metre and a water-cement ratio no higher than 0.85.
- Reinforced foundations are not a guess: the grade comes from the engineer or designer, working to I.S. EN 206 and its Irish National Annex.
- A 1:7 cement to aggregate mix by volume is allowed for small projects, but for a house, specified ready mix gives you consistent quality.
- Measure the volume, check lorry access, give your supplier notice, and decide early whether you need a pump.
- Place in layers, compact well and cure the concrete. Strength builds over about 28 days.
What “foundation concrete mix” actually means
When people search for a foundation mix they usually expect a recipe: so many shovels of cement, sand and gravel. Many pages online offer exactly that, with ratios such as 1:2:3 or 1:3:6. Those figures come from general guides, and they are not what Irish building guidance asks of a house foundation.
In Ireland, the question is answered by a strength class. Concrete is described by a letter and two numbers, such as C12/15. The first number is the strength a cylinder sample should reach, and the second is the strength of a cube sample, both in newtons per square millimetre after 28 days. Choosing a foundation mix means choosing the class, then ordering concrete made to that class.
The key documents are Technical Guidance Document A (Structure), part of the Building Regulations 2012 guidance, and the standard I.S. EN 206. The Irish Concrete Society explains that I.S. EN 206-1 replaced IS 326 Part 2 in December 2003 as the national standard for specifying and producing concrete. Its Irish National Annex is where guidance on concrete quality and cover to reinforcement sits.
The strength class for plain strip foundations
For plain concrete strip foundations in non-aggressive ground, TGD A calls for Class C12/15, with a minimum cement content of 200 kg/m³ and a maximum water-cement ratio of 0.85. That is the floor, not a target to aim for.
Three terms in that sentence matter:
- Plain means no steel reinforcement in the foundation.
- Non-aggressive ground means soil and groundwater without chemicals, such as sulphates, that attack concrete. If your site investigation says otherwise, the standard mix is no longer enough.
- Water-cement ratio is the weight of water against the weight of cement. More water makes concrete easier to pour, but weaker and less durable.
If you are comparing quotes, ask for the class in the quote, not a vague description such as “foundation mix”. It keeps everyone on the same page, including your building control officer and your engineer.
Reinforced foundations and aggressive ground
Rafts, reinforced strips, pad foundations, ground beams and anything with steel in it need more than the plain strip rule. The guidance states that reinforced foundations must follow the grade specifications in Table NA.5 of I.S. EN 206-1:2002. The same applies where ground conditions are aggressive.
In practice you will not pick from that table yourself. The structural engineer or designer works out the class from the foundation type, the cover to the steel and the ground conditions, and writes it on the drawings. Concrete selection depends on foundation type and ground conditions, and the engineer must confirm the specification before any pour. If the drawings are unclear, or the ground you find when you dig is different from what the report described, stop and ask before the lorry arrives. It is far cheaper to make a phone call than to break out a poured foundation.
Quick guide: which mix for which situation
| Situation | What the guidance points to | Who decides |
|---|---|---|
| Plain strip foundation, non-aggressive ground | C12/15 minimum, 200 kg/m³ cement, water-cement ratio 0.85 maximum | Designer, checked against TGD A |
| Reinforced strip, raft or pad foundation | Grade from I.S. EN 206-1 and its Irish National Annex | Structural engineer |
| Aggressive or chemically active ground | Specification under I.S. EN 206, not the plain strip rule | Structural engineer |
| Small job, plain foundation, volumetric mixing | 1:7 cement to aggregate by volume permitted | Designer, with care over batching |
All rows come from the same Irish guidance: TGD A within the Building Regulations 2012.
Site-mixed 1:7 or ready mix?
TGD A allows a 1:7 cement to aggregate mix by volume as an alternative to the specified C12/15 grade, for small projects with plain foundations. It was written with a garden wall or a small outbuilding in mind, not a family home.
The trouble with mixing on site is consistency. Quality depends on the same ratio, the same water content and the same admixture dose in every batch, and a tired crew at the end of the day will not always hit them. Selfbuild.ie notes that most contractors use ready-mixed concrete for this reason. For larger or more critical structural work, the guidance is to use specified ready mix because it gives quality, strength and durability that volumetric mixing struggles to match.
There is also a paperwork benefit. Under I.S. EN 206-1, the manufacturer is responsible for conformity and must provide a Declaration of Conformity with every delivery of ready-mixed concrete. Keep those delivery documents. They show the class you ordered is the class you received, which can matter if anyone asks later.
Our own view is simple: for a house, order ready mix. Our ready mix concrete supply and delivery is made for exactly this, and you tell us the class from your drawings.
Small pours and awkward quantities
Not every foundation job needs a full-size lorry. A garage base, a porch, a small extension or a boundary wall footing may need only a couple of cubic metres. For those, mini mix concrete delivery can be a better fit, because a smaller truck gets into tighter spaces and you order closer to the volume you need. Even then, quote the class from the drawings. A small job is still a foundation.
How to work out how much concrete you need
The volume is length times width times depth, in metres, for every part of the foundation. For a strip foundation, measure the total run of trench, then multiply by the width and the depth of concrete. Add the pads, thickenings and any ground beams as separate sums, then add them up.
The British Ready Mixed Concrete Association advises that you measure the prepared area and calculate the required volume, and give the supplier as much notice as possible. Two habits help:
- Measure after the trench is dug, not from the drawing. Trenches rarely come out to the exact dimension, especially in soft or stony ground.
- Allow a sensible margin. Ground is uneven, and running short mid-pour leaves a cold joint in the foundation, which is a far bigger problem than a little concrete left over.
If you are unsure, tell us the dimensions and we will talk it through with you before you confirm the order.
Delivery day: what to check
A good foundation pour is mostly decided the day before. These are the points we ask every customer to confirm.
Access for the lorry
The BRMCA guide says to ensure the truck has suitable, stable and safe access. A loaded mixer is heavy. Soft verges, new drainage runs, narrow gates and overhead cables are all worth checking. If the lorry cannot get to the trench, you have two choices: move the concrete by barrow, or pump it.
Timing
Concrete should normally be delivered within two hours of loading in truck mixers or agitators. The limit can be longer in cold conditions and shorter in very hot weather. So the trench must be ready, inspected and signed off before the lorry is on the road, with enough people on site to place the concrete as it arrives.
Pumping
If the truck cannot discharge directly, the same guide says a pump is usually more efficient for larger volumes. It also saves labour and keeps the pour moving. We offer both options:
- A concrete boom pump reaches over fences, hedges and parts of the site the lorry cannot enter.
- Concrete line pumping sends concrete through hoses to back gardens, long sites or places with tight access.
Backyard foundations, terraced houses and infill sites are the usual cases where a pump pays for itself. Our restricted access concrete pumping page covers those tougher sites.
Placing, compacting and curing the foundation
The concrete you order is only as good as the way it goes in. The BRMCA guidance says to place concrete in roughly equal layers, normally 300 to 500 mm deep, and to compact each layer with a vibrator. A deep foundation poured in one go, with no compaction, can trap air and leave weak spots.
Do not add water on site to make it flow more easily. It raises the water-cement ratio above the figure the class assumes and weakens the foundation. If the mix feels stiff, talk to your supplier about the consistency before the pour, not during it.
Cold weather
Fresh concrete should be at least 5°C at delivery, and in cold weather it should be insulated after placing. Irish winters make this a real consideration for foundations poured between October and March. If frost is forecast, talk to your engineer and supplier about timing.
Curing
Proper curing stops moisture escaping while keeping the concrete at a satisfactory temperature. The BRMCA lists polythene sheeting or a sprayed membrane as ways to do it. Concrete usually takes 28 days to reach its target strength, which is why the class is defined at that age. Your engineer will tell you when it is safe to build up from the foundation.
Our perspective
We have supplied and pumped concrete for more than 30 years, and the same few things come up on foundation jobs again and again. The most common is a customer who has been told a recipe, such as a ratio from the internet, when what they need is a class from their engineer. We would always rather you phone us with the class, the volume and the site address, and let us handle the rest.
The second is access. Many foundation trenches in Leinster are at the back of a house, down a narrow side passage, or behind a boundary wall. Pumping turns that from a day of barrowing into a controlled pour, and it keeps the crew fresh enough to finish the job properly. We are a family-run business, and we take the time to ask the dull questions up front, because they save you the stressful ones on the day.
Our advice for a house build is straightforward. Get the specification from your engineer, order ready mix to that class, check access, and bring in a pump if the lorry cannot reach. Do that, and the foundation does what it should: it gives the whole building a solid base.
Ordering foundation concrete from GS Concrete Pumping
We supply ready mix concrete and pumping across Leinster for builders, developers and private homeowners. Tell us the strength class on your drawings, the quantity and the site address, and we will advise on the right lorry and whether a pump makes sense. If you are not sure which service fits, start with our concrete pumping services page, or contact us through the GS Concrete Pumping site.
You can read more about how we work and our background on our company page. Prices depend on the class, volume, distance and whether a pump is needed, so we quote each job individually.
FAQ
What is the best concrete mix for house foundations?
There is no single best mix. For plain strip foundations in non-aggressive ground, the minimum is C12/15. For reinforced foundations the structural engineer specifies the class under I.S. EN 206. Order the class written on your drawings from a ready mix supplier.
Can I mix foundation concrete myself?
For small projects with plain foundations, TGD A permits a 1:7 cement to aggregate mix by volume. For a house, quality and consistency are hard to control batch by batch, so most contractors order ready mix. Ask your engineer before you decide.
How long before I can build on the foundation?
Concrete usually takes 28 days to reach its target strength, but your engineer decides when loading is safe. Cure the concrete properly in the meantime, covering it with polythene or using a sprayed membrane to stop it drying out.
Do I need a pump for foundation concrete?
You need one if the lorry cannot get close enough to discharge into the trench, or if the volume makes barrowing slow. A pump is usually more efficient for larger volumes. Measure the site and check access before you book.